WAPA HOLDS OFF ROTATION

The V.I. Water and Power Authority will not rotate St. Croix feeders Monday and Tuesday as previously announced.
WAPA instead has rescheduled permanent repairs to the Richmond Power Plant for this coming weekend, July 24 – July 26.
WAPA's problems began just after 5 p.m. Sunday, July 11 when an electrical short developed on high voltage cables at the Richmond substation and tripped the operating generators and desalinization units.
The mishap forced the St. Croix into an island-wide outage followed by the feeder rotation.

Print Friendly, PDF & Email
Keeping our community informed is our top priority.
If you have a news tip to share, please call or text us at 340-228-8784.

Support local + independent journalism in the U.S. Virgin Islands

Unlike many news organizations, we haven't put up a paywall – we want to keep our journalism as accessible as we can. Our independent journalism costs time, money and hard work to keep you informed, but we do it because we believe that it matters. We know that informed communities are empowered ones. If you appreciate our reporting and want to help make our future more secure, please consider donating.