Phase 1 of King Airport Parking Garage Construction to Start March 8

A rendering of the Cyril E. King Airport’s new Parking and Transportation Center (Submitted photo)

Construction of the Cyril E. King Airport’s new Parking and Transportation Center will begin on Monday, March 8. During the first phase of construction, the project contractor will relocate underground pipes and sewage lines.

Most of the airport’s public parking area is now closed and will remain closed during the duration of the two-year project. The V.I. Port Authority announced last month that this project would start in March and parking at the Cyril E. King Airport will be limited during construction. Travelers have been advised to be dropped off and picked up when traveling.

Curbside parking is not allowed at the airport when dropping off or picking up passengers. Signs are posted at the terminal advising of the new parking restrictions. Motorists are asked to adhere to the no parking signs as violators will be towed and booted at their own expense.

VIPA Executive Director Carlton Dowe said that the authority is aware that the limited parking at CEKA during construction will be an inconvenience to the public.

“We are asking for the public’s patience during this temporary arrangement. After the Parking and Transportation Center is completed, we will be able to relocate the car rental agencies and begin the much-needed expansion of the 30-year-old CEKA terminal,” he said.

Cyril E. King Airport’s plans for construction phases (Submitted photo)

The Parking and Transportation Center will have 600 parking spaces and a dedicated location for ground transportation and car rental operations. The $26.8 million project is funded via a $20M grant from the U.S. Department of Commerce-Economic Development Administration in 2019. VIPA will provide a $6.8 million local match. AT Construction was awarded the contract via a competitive bidding process.

VIPA will continue to provide project updates via its website at www.viport.com, its social media accounts and through press releases and radio announcements.

Print Friendly, PDF & Email
Keeping our community informed is our top priority.
If you have a news tip to share, please call or text us at 340-228-8784.

Support local + independent journalism in the U.S. Virgin Islands

Unlike many news organizations, we haven't put up a paywall – we want to keep our journalism as accessible as we can. Our independent journalism costs time, money and hard work to keep you informed, but we do it because we believe that it matters. We know that informed communities are empowered ones. If you appreciate our reporting and want to help make our future more secure, please consider donating.

UPCOMING EVENTS