Crews will be assigned to the following priority work areas this week, Jan. 15-19 and into the weekend, finalizing reconstruction and restoration of customers:
St. Croix: Blue Mountain, Brooks Hill, Bugby Hole, Cane Bay, Glynn, Grapetree Bay, Great Pond, Hannah’s Rest, Herbert Grigg, Hibiscus Point, Jolly Hill, Judith’s Fancy, La Grange, La Reine, Little Fountain, Little La Grange, Mon Bijou, Mount Pellier, Orange Grove, Peter’s Rest, Plessen River, Salt River, Seven Hills, Sion Farm, Springfield, St. John and Two Friends.
St. Thomas: Frenchman’s Bay, Lilliendahl and Marienhoj, Wintberg and Tabor and Harmony.
St. John: Calabash Boom to Mandahl, Lameshur Estate and East End Road.
In addition, crews are continuing to replace streetlights along major thoroughfares on all three islands and are working to restore electric service to traffic signals.